The Eklutna River Bridge Replacement Project has moved to construction. Below is the anticipated construction schedule:
Schedule for the Eklutna River Bridge Replacement Project
August 2013 – September 2013
- Project Start Up
- Planning and Concept Phase
- Problem Identification – Open House #1 (September 12, 2013)
- Draft Concept Report
- Planning and Zoning Commission (PZC) Review November 4, 2013
October 2013 – Feburary 2014
- Preliminary Engineering including surveying & geotechnical field studies
- Design Study Phase
- Design Study Report (35% DSR)
- Design Alternatives Evaluation – Open House #2 (tentative December 2013)
- Planning and Zoning Commission (PZC) Review March 2014 (tentative)
March 2014 – August 2014
- Preliminary Design of Approved Preferred Alternative (65%)
- Preliminary Design – Open House #3
- Urban Design Commission (UDC) Review Fall 2014 (tentative)
September 2014 – December 2014
- Final Design (95%)
- Final Design & Preconstruction – Open House #4
Winter 2014 – Spring 2015
- Bid Phase
Spring 2015 – Fall 2015
- Bridge Removal & Construction Start