Schedule

The Eklutna River Bridge Replacement Project has moved to construction.  Below is the anticipated construction schedule:

Eklutna River Bridge Construction Schedule

 

Schedule for the Eklutna River Bridge Replacement Project

August 2013 – September 2013

  • Project Start Up
  • Planning and Concept Phase
  • Problem Identification –  Open House #1 (September 12, 2013)
  • Draft Concept Report
  • Planning and Zoning Commission (PZC) Review November 4, 2013

October 2013 – Feburary 2014

  • Preliminary Engineering including surveying & geotechnical field studies
  • Design Study Phase
  • Design Study Report (35% DSR)
  • Design Alternatives Evaluation – Open House #2 (tentative December 2013)
  • Planning and Zoning Commission (PZC) Review March 2014 (tentative)

March 2014 – August 2014

  • Preliminary Design of Approved Preferred Alternative (65%)
  • Preliminary Design – Open House #3
  • Urban Design Commission (UDC) Review Fall 2014 (tentative)

September 2014 – December 2014

  • Final Design (95%)
  • Final Design & Preconstruction – Open House #4

Winter 2014 – Spring 2015

  • Bid Phase

Spring 2015 – Fall 2015

  • Bridge Removal & Construction Start